2008
Impregilo v. Argentina (II) Impregilo S.p.a v. Argentine Republic (II) (ICSID Case No. ARB/08/14)
Argentina
Italy
Rights under a highway construction concession agreement held by Impregilo's local subsidiary Camino de las Sierras.
Claims arising out of Argentina's enactment of a 'pesification' law, the freeze on toll rates, among other measures adopted during its 2001-2002 economic crisis, allegedly affecting claimant's investment in a highway construction project to build and manage roads to the city of Córdoba.
Tertiary: F - Construction
42 - Civil engineering
ICSID (International Centre for Settlement of Investment Disputes)
ICSID (International Centre for Settlement of Investment Disputes)
Danelius, H.
Brower, C. N.
Hossain, K.
Order for the discontinuance of the proceeding issued by the Tribunal dated 27 October 2010, pursuant to ICSID Arbitration Rule 43(1)
250.00 mln USD
Data not available
Data not available
Not applicable - settled or discontinued before decision on liability
None